Construction Bulletin Week of October 8 to12

Odegaard construction during the week of October 8-12 will include:

1. Framing of soffits on the 2nd floor inside the construction barrier. Expect increased noise due to cutting and fastening of materials.

2. Ongoing mechanical and electrical system rough-in and installation. Normal construction noise levels.

3. Concrete work to finish steel stairs on the 1st floor inside the construction barrier. Normal construction noise levels.

4. Layout and preparation work on the 3rd floor outside of the construction barrier primarily during early morning hours.

Construction work happens between 6am and 3pm, Monday through Friday.

Leave a Reply

Your email address will not be published. Required fields are marked *

Required
Required