The main construction activities for the week of November 5– 9 are the following:
- Framing of soffits on the 3rd floor outside of the construction barrier. Increased noise level for cutting and fastening of materials. Work hours will be from 5:00 am to 1:30 pm.
– Ongoing mechanical and electrical system rough-in and installation on the 1st floor and mezzanine. Normal construction noise levels.
- Floor 3 soffit mechanical and electrical rough-in outside of construction barrier. Work hours will be from 5:00 to 1:30 pm.
– Installation of glass wall system header track on 3rd floor soffits to allow drywall installation. Work hours will be from 5:00 to 1:30 pm.
– Plumbing system modifications on the Friday night and Saturday morning when library closed.
The following construction activities will be starting next week of November 12 — November 16.
- Ongoing mechanical and electrical system rough-in and installation on the 1st floor and mezzanine. Normal construction noise levels.
– Floor 3 soffit mechanical and electrical rough-in outside of construction barrier. Work hours will be from 5:00 to 1:30 pm.
– Stocking of drywall and installation of drywall at soffits on 3rd floor both inside and outside of barrier. Increased noise level for screw guns, etc. Work hours will be from 5:00 am to 1:30 pm.
- Completion of framing of floor 3 soffits outside of the construction barrier. Increased noise level for cutting and fastening of materials. Work hours will be from 5:00 am to 1:30 pm.