Construction Bulletin November 5-9

The main construction activities for the week of November 5- 9 are the following:

–  Framing of  soffits on the 3rd floor outside of the construction barrier. Increased noise level for cutting and fastening of materials.  Work hours will be from 5:00 am to 1:30 pm.
–  Ongoing mechanical and electrical system rough-in and installation on the 1st floor and mezzanine. Normal construction noise levels.
 –   Floor 3 soffit mechanical and electrical rough-in outside of construction barrier. Work hours will be from 5:00 to 1:30 pm.
–  Installation of glass wall system header track on 3rd floor soffits to allow drywall installation. Work hours will be from 5:00 to 1:30 pm.
–  Plumbing system modifications on the Friday night and Saturday morning when library closed.

The following construction activities will be starting next week of November 12 – November 16.

 – Ongoing mechanical and electrical system rough-in and installation on the 1st floor and mezzanine. Normal construction noise levels.
–  Floor 3 soffit mechanical and electrical rough-in outside of construction barrier. Work hours will be from 5:00 to 1:30 pm.
– Stocking of drywall and installation of drywall at soffits on 3rd floor both inside and outside of barrier. Increased noise level for screw guns, etc. Work hours will be from 5:00 am to 1:30 pm.
 – Completion of framing of floor 3 soffits outside of the construction barrier. Increased noise level for cutting and fastening of materials.  Work hours will be from 5:00 am to 1:30 pm.

Leave a Reply

Your email address will not be published. Required fields are marked *

Required
Required