Construction Bulletin November 12–16

The main con­struc­tion activ­i­ties for the week of Novem­ber 12– 16 are the following:

-  Stock­ing of dry­wall and instal­la­tion of dry­wall at sof­fits on the 3rd floor both inside and out­side of bar­rier. Increased noise level for screw guns, etc. Work hours will be from 5:00 am to 1:30 pm.
– Com­ple­tion of fram­ing of level 3 sof­fits out­side of the con­struc­tion bar­rier. Increased noise level for cut­ting and fas­ten­ing of mate­ri­als.  Work hours will be from 5:00 am to 1:30 pm.
–  Ongo­ing mechan­i­cal and elec­tri­cal sys­tem rough-in and instal­la­tion on the 1st floor and mez­za­nine. Nor­mal con­struc­tion noise lev­els.
 -   Third floor sof­fit mechan­i­cal and elec­tri­cal rough-in out­side of con­struc­tion bar­rier. Work hours will be from 5:00 to 1:30 pm.
–  Instal­la­tion of glass wall sys­tem header track on 3rd floor sof­fits to allow dry­wall instal­la­tion. Work hours will be from 5:00 to 1:30 pm.