Construction Bulletin November 19–21

The main con­struc­tion activ­i­ties in the Ode­gaard Under­grad­u­ate Library for the week of Novem­ber 19– 23 are the fol­low­ing: (There will be no work on Thurs­day 11/22 or Fri­day 11/23).

-  Ongo­ing mechan­i­cal and elec­tri­cal sys­tem rough-in and instal­la­tion on floor 1 and mez­za­nine level. Nor­mal con­struc­tion noise lev­els.
 - Instal­la­tion of dry­wall at sof­fits on the 3rd floor both inside and out­side of bar­rier. Increased noise level for screw guns, etc. Work hours from 5:00 am to 1:30 pm.
 - Tap­ing and fin­ish­ing of dry­wall sof­fits both inside and out­side of bar­rier. Work hours will be from 5:00 am to 1:30 pm.
 - Com­ple­tion of fram­ing on floor 2 sof­fits on south side. Some early morn­ing work out­side of bar­rier from 5:00 am to 1:30 pm.will be from 5:00 am to 1:30 pm.

The fol­low­ing con­struc­tion activ­i­ties will be start­ing next week of Novem­ber 26 — Novem­ber 30

 - Fram­ing of walls and ceil­ings on mez­za­nine level.  Nor­mal con­struc­tion noise lev­els.
– Tap­ing and fin­ish­ing of dry­wall sof­fits both inside and out­side of bar­rier. Work hours will be from 5:00 am to 1:30 pm.
 - Instal­la­tion of dry­wall at sof­fits on level 2 on both sides of bar­rier. Any work out­side bar­rier will be from 5:00 am to 9:00 am.
– Start of paint­ing on 3rd floor inside of bar­rier in prepa­ra­tion for wood ceil­ing instal­la­tion. Work hours from 5:00 am to 1:30 pm.
– Early morn­ing mechan­i­cal work and ceil­ing work on ground floor from 5:00 am to 9:00 am.