Construction Bulletin November 19-21

The main construction activities in the Odegaard Undergraduate Library for the week of November 19- 23 are the following: (There will be no work on Thursday 11/22 or Friday 11/23).

–  Ongoing mechanical and electrical system rough-in and installation on floor 1 and mezzanine level. Normal construction noise levels.
 – Installation of drywall at soffits on the 3rd floor both inside and outside of barrier. Increased noise level for screw guns, etc. Work hours from 5:00 am to 1:30 pm.
 – Taping and finishing of drywall soffits both inside and outside of barrier. Work hours will be from 5:00 am to 1:30 pm.
 – Completion of framing on floor 2 soffits on south side. Some early morning work outside of barrier from 5:00 am to 1:30 pm.will be from 5:00 am to 1:30 pm.

The following construction activities will be starting next week of November 26 – November 30

 – Framing of walls and ceilings on mezzanine level.  Normal construction noise levels.
– Taping and finishing of drywall soffits both inside and outside of barrier. Work hours will be from 5:00 am to 1:30 pm.
 – Installation of drywall at soffits on level 2 on both sides of barrier. Any work outside barrier will be from 5:00 am to 9:00 am.
– Start of painting on 3rd floor inside of barrier in preparation for wood ceiling installation. Work hours from 5:00 am to 1:30 pm.
– Early morning mechanical work and ceiling work on ground floor from 5:00 am to 9:00 am.